1FORMWORKS
1.1Form Assembly
2.1.1Form joints/seams shall have no grout leaking. Before placing concrete, form board shall be moistened with water, but no water deposit.
2.1.2 Form material shall be either steel, plywood, plastic, etc, the supporting frame shall be steel, and the material property shall comply with the current national standards. 2.1.3 The contact surface between the forms and concrete shall be cleaned and applied with separating agent.
2.1.4 Before placing concrete, the foreign matters in the forms shall be cleaned.
2.1.5 When the cast-in place reinforced concrete girder/slabs with span no less than 4 meters; its forms shall be arched according to design requirement. When there is no clear design requirement, the arch camber height shall be 1/1000-3/1000 of the span.
2.1.6 The built-in embedded parts and reserved holes/openings fixed on the forms shall not be omitted, and shall be fixed firmly. Their deviation shall comply with table 1. Table 1 Allowable tolerance of embedded parts and reserved openings/holes
|