目 录 1 工程概况.........................................................................................................................................1 1.1 软基处理分项工程简介.........................................................................................................1 1.2 本标段软基处理设计概况......................................................................................................1 1.2.1 地质条件.........................................................................................................................1 1.2.2 工程特点.........................................................................................................................2 1.3 施工条件................................................................................................................................2 1.3.1 交通条件.........................................................................................................................2 1.3.2 临时水电.........................................................................................................................2 1.3.3 人员机械及材料.............................................................................................................3 1.4 工程量....................................................................................................................................3 2 施工布置.........................................................................................................................................4 2.1 施工管理组织.........................................................................................................................4 2.2 施工前的准备工作.................................................................................................................5 2.3 工期安排和施工进度计划图..................................................................................................5 3 主要施工方法.................................................................................................................................6 3.1 施工测量................................................................................................................................6 3.1.1 准备工作与过程控制.....................................................................................................6 3.1.2 道路控制.........................................................................................................................7 3.1.3 保证测量精度的措施.....................................................................................................7 3.2 软基处理................................................................................................................................8 3.2.1 软基处理技术要求.........................................................................................................8 3.2.2 插板排水堆载顶压处理.................................................................................................8 3.2.3 换填堆载处理...............................................................................................................13 3.2.4 换填碾压处理...............................................................................................................14 3.2.5 不同处理方法的衔接及其它.......................................................................................14 3.2.6 观测与监测...................................................................................................................14 3.3 路基施工...............................................................................................................................16 3.3.1 路基排水.......................................................................................................................16 3.3.2 土方填筑施工...............................................................................................................16 3.3.3 路基压实要求...............................................................................................................17 4 施工流程.......................................................................................................................................19 4.1 插板排水堆载预压施工工艺框图........................................................................................19 4.2 塑料排水板施工工艺框图....................................................................................................20 4.3 换填堆载预压施工工艺框图................................................................................................21 4.4 道路路基施工工艺框图.......................................................................................................22 5 确保工程质量的措施....................................................................................................................23 5.1 保证质量的管理措施...........................................................................................................23 5.2 确保施工质量的技术措施....................................................................................................23 6 确保安全生产的措施....................................................................................................................24 7 确保文明施工的措施....................................................................................................................25 7.1 文明施工的组织保障...........................................................................................................25 7.2 文明施工的保证措施...........................................................................................................25 8 确保工期的措施............................................................................................................................28 8.1 工期的控制方法...................................................................................................................28 8.2 保证工期的技术措施...........................................................................................................28
8.3 保证工期的组织与管理措施................................................................................................29 9 雨季施工的工作安排....................................................................................................................30 9.1 施工组织...............................................................................................................................30 9.2 技术措施...............................................................................................................................30
1 1 工程概况 1.1 软基处理分项工程简介 深圳市**大道北二段Ⅲ标段市政工程,工程地点位于**区**镇。**大道是**区 西部的一条南北向Ⅰ级客运主干道,道路控制红线宽度100 米,本标段工程桩号为 K11+320—13+320,但不含k11+920—12+440**河桥段,中线长1480 米,沿途与广深高 速公路辅道、松明大道、沙江路相交。由于全线均为软基,故需要进行软基处理。 路基软基处理根据各个部分地质情况的不同,分别采用换填碾压、换填堆载、插板 排水固结三种处理方式。
|
|